NATIONAL GAS PIPELINE
PHASE 1, SECTION 1
RIGHT OF WAY


Client: Iran National Gas Company
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 35,000,000,000.00 Rls
Contract Duration: 15 months
Personnel Employed: 185 persons

Contract Items

No. Contract Item Unit Contract Quantity Executed Quantity
1 Excavation – Soil M3 1,040,000 2,100,000
2 Excavation – Rock M3 1,220,000 1,800,000
3 Transportation M3 2,200,000 3,900,000