SOUTH PARS GAS FIELD DEVELOPMENT
PHASES 6, 7 & 8
SITE PREPARATION


Client: Petro-Pars Company
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 140,999,000,000.00 Rls
Contract Duration: 10 months
Personnel Employed: 890 persons

Bill of Quantities

No. Contract Item Unit Contract Quantity Executed Quantity
1 Top Soil M3 430,000 480,000
2 Excavation Ground in any class/condition M3 4,450,000 4,500,000
3 Embankment/Backfill M3 2,500,000 2,700,000
4 Transportation M3 - km 31,800,000 34,142,040
5 Rip - Rap M2 130,000 171,000
6 Fencing M 13,400 4,900
7 Culverts:Excavation M3 620 1,284
8 Roads: Asphalt Concrete Layer M2 - CM 270,000 260,800
9 Roads: Crush Rock Base Layer M3 6,660 9,360
10 Roads: Granular Sub – base (GSB) M3 22,770 28,785
11 Earthen Ditches M3 16,500 17,565
12 Concrete Lining of Ditches M3 5,000 5,577
13 Stone Masonry Lining of Ditch M3 1,000 3,252

The South Pars Gas field, phases 6,7,8 Site Preparation Project Comprises of the Following main parts:
  1. Plant Area.
    • Bulk excavation to establish platforms on which different parts of Refinery facilities shall be located.
    • Compaction of Excavated Surfaces and Filled Areas.
    • Slope Protection around Platforms using Stone Pitching.
    • Construction of all around the Site Fencing and Gates.
    • Construction of Surface Runoff Collection System..
    • Construction of Main Internal Roads.
  2. Flare Area
    • Bulk excavation to establish platforms.
    • Compaction of Excavated Surfaces and Filled Areas.
    • Access Road To Flare Areas.
  3. Camp-2 Area
    • Bulk excavation to establish platforms.
    • Compaction of Excavated Surfaces and Filled Areas.
    • All around the site Fencing and Gates.


SOUTH PARS GAS FIELD DEVELOPMENT
PHASES 4, 5
FLARE AREA


Client: HYUNDAI Company
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 2,709,500.00 USD
Contract Duration: 6 months
Personnel Employed: 300 persons

Bill of Quantities

No. Contract Item Unit Contract Quantity Executed Quantity
1 Filling M3 210,000 118,500
2 Cutting M3 750,000 580,000
3 Rock Blasting/ Excavation M3 420,000 250,000
4 Disposal M3 120,000 110,000


SOUTH PARS GAS FIELD DEVELOPMENT
PHASES 4, 5
MAIN PLANT, AREA A


Client: HYUNDAI Company
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 2,200,000.00 USD
Contract Duration: 4 months
Personnel Employed: 250 persons

Bill of Quantities

No. Contract Item Unit Contract Quantity Executed Quantity
1 Excavation - Soil M3 61,154

 

2 Backfill M3 34,559

 

3 Disposal M3 26,595

 

4 Concrete (fc=25N/mm2) M3 12,921

 

5 Concrete (fc=35N/mm2) M3 693

 

6 Formwork M2 27,604

 

7 Re – Bar (ASTM A615) Ton 1,292

 

8 Water Stop M 598

 

9 Cutting M3 88,536

 

10 Filling (Cutting Soil) M3 88,536

 


   

SOUTH PARS GAS FIELD DEVELOPMENT
DYNAMIC COMPACTION ON RECLAIMED LAND


Client: Petrochemical National Company
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 6,400,000,000.00 Rls
Contract Duration: 7 months
Personnel Employed: 30 persons

Bill of Quantities

No. Contract Item Unit Contract Quantity Executed Quantity
1 Compaction – 1st Layer M2 60,000

 

2 Backfill M3 180,000

 

3 Compaction – 2 nd Layer M2 60,000

 




SOUTH PARS GAS FIELD DEVELOPMENT
PERPENDICULAR TO COAST JETTY


Client: Petrochemical National Company
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 1,900,000,000.00 Rls
Contract Duration: 1.5 months
Personnel Employed: 150 persons

Bill of Quantities

No. Contract Item Unit Contract Quantity Executed Quantity
1 Extract, Load, Transport, Dispose, Grade & Compact M2 60,000
  0 – 100 kg M3 35,000 35,000
  100 – 500 kg M3 13,000 13,000
  0.5 – 3 Tons M3 5,000 5,000
  Greater than 3 Tons M3 2,000 2,000


SOUTH PARS GAS FIELD DEVELOPMENT
BANK CONSTRUCTION & LAND GRADING


Client: Petrochemical National Company
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 2,000,000,000.00 Rls
Contract Duration: 1.5 months
Personnel Employed: 60 persons

Bill of Quantities

No. Contract Item Unit Contract Quantity Executed Quantity
1 Extract, Load, Transport, Dispose, PUSH, Grade
  Soil & Rock Material M3 400,000 400,000

 


SOUTH PARS GAS FIELD DEVELOPMENT
PHASES 6, 7 & 8
Camp3


Top soil: 23,489 m3
Cut: 651,051 m3
Filling: 600,000 m3
Fencing: 4000 m3
Engineering: %6 contract price

 


SOUTH PARS GAS FIELD DEVELOPMENT
PHASES 6, 7 & 8
CIVIL WORK IN FLARE AREA


Client: Joint venture of TEC / IDRO / JGC/DIC
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 20,000,000,000 RLS
Contract Duration: 8.5 months
Personnel Employed: 250 persons

Bill of Quantities

Rebar: 348 tons
Embedded steel plate: 54 tons
Form work: 11,234 m2
Concrete: 5,000 m3
Stone pitching: 50,000 m2
Gabion : 9,000 m3

 


SOUTH PARS GAS FIELD DEVELOPMENT
EARTH WORK IN FLARE AREA


Client: Joint venture of TEC / IDRO / JGC/DIC
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 25,000,000,000 RLS
Contract Duration: 6 months
Personnel Employed: 90 persons

Bill of Quantities

Cutting: 214,017 m3
Cutting by hammer: 29,897 m3
Fill: 33,785 m3
Disposal: 208,767 m3



SOUTH PARS GAS FIELD DEVELOPMENT
PHASE 9, 10
SITE PREPARATION WORKS FOR FLARE ROUTE


Client: Oil industries engineering and construction (OIEC)
Contractor: FKJ
Site Location: Boushehr – Asalooyeh
Contract Price: 7,400,000,000 Rls
Contract Duration: 5 months
Personnel Employed: 80 persons

Bill of Quantities

Cutting: 130,000 m3
Cutting by hammer: 10,000m3
Blasting: 60,000m3
Disposal: 100,000m3
Filling: 50,000 m3