 SOUTH PARS GAS FIELD DEVELOPMENT
PHASES 6, 7 & 8
SITE PREPARATION
| Client: |
Petro-Pars Company |
| Contractor: |
FKJ |
| Site Location: |
Boushehr – Asalooyeh |
| Contract Price: |
140,999,000,000.00 Rls |
| Contract Duration: |
10 months |
| Personnel Employed: |
890 persons |
Bill of Quantities
| No. |
Contract Item |
Unit |
Contract
Quantity |
Executed Quantity |
| 1 |
Top Soil |
M3 |
430,000 |
480,000 |
| 2 |
Excavation
Ground in any class/condition |
M3 |
4,450,000 |
4,500,000 |
| 3 |
Embankment/Backfill |
M3 |
2,500,000 |
2,700,000 |
| 4 |
Transportation |
M3 - km |
31,800,000 |
34,142,040 |
| 5 |
Rip - Rap |
M2 |
130,000 |
171,000 |
| 6 |
Fencing |
M |
13,400 |
4,900 |
| 7 |
Culverts:Excavation |
M3 |
620 |
1,284 |
| 8 |
Roads: Asphalt Concrete Layer |
M2 - CM |
270,000 |
260,800 |
| 9 |
Roads: Crush Rock Base Layer |
M3 |
6,660 |
9,360 |
| 10 |
Roads: Granular Sub – base (GSB) |
M3 |
22,770 |
28,785 |
| 11 |
Earthen Ditches |
M3 |
16,500 |
17,565 |
| 12 |
Concrete Lining of Ditches |
M3 |
5,000 |
5,577 |
| 13 |
Stone Masonry Lining of Ditch |
M3 |
1,000 |
3,252 |
The South Pars Gas field, phases 6,7,8 Site Preparation Project Comprises of the Following main parts:
- Plant Area.
- Bulk excavation to establish platforms on which different parts of Refinery facilities shall be located.
- Compaction of Excavated Surfaces and Filled Areas.
- Slope Protection around Platforms using Stone Pitching.
- Construction of all around the Site Fencing and Gates.
- Construction of Surface Runoff Collection System..
- Construction of Main Internal Roads.
- Flare Area
- Bulk excavation to establish platforms.
- Compaction of Excavated Surfaces and Filled Areas.
- Access Road To Flare Areas.
- Camp-2 Area
- Bulk excavation to establish platforms.
- Compaction of Excavated Surfaces and Filled Areas.
- All around the site Fencing and Gates.
SOUTH PARS GAS FIELD DEVELOPMENT
PHASES 4, 5
FLARE AREA
| Client: |
HYUNDAI Company |
| Contractor: |
FKJ |
| Site Location: |
Boushehr – Asalooyeh |
| Contract Price: |
2,709,500.00 USD |
| Contract Duration: |
6 months |
| Personnel Employed: |
300 persons |
Bill of Quantities
| No. |
Contract Item |
Unit |
Contract
Quantity |
Executed Quantity |
| 1 |
Filling |
M3 |
210,000 |
118,500 |
| 2 |
Cutting |
M3 |
750,000 |
580,000 |
| 3 |
Rock Blasting/
Excavation |
M3 |
420,000 |
250,000 |
| 4 |
Disposal |
M3 |
120,000 |
110,000 |
SOUTH PARS GAS FIELD DEVELOPMENT
PHASES 4, 5
MAIN PLANT, AREA A
| Client: |
HYUNDAI Company |
| Contractor: |
FKJ |
| Site Location: |
Boushehr – Asalooyeh |
| Contract Price: |
2,200,000.00 USD |
| Contract Duration: |
4 months |
| Personnel Employed: |
250 persons |
Bill of Quantities
| No. |
Contract Item |
Unit |
Contract
Quantity |
Executed Quantity |
| 1 |
Excavation - Soil |
M3 |
61,154 |
|
| 2 |
Backfill |
M3 |
34,559 |
|
| 3 |
Disposal |
M3 |
26,595 |
|
| 4 |
Concrete (fc=25N/mm2) |
M3 |
12,921 |
|
| 5 |
Concrete (fc=35N/mm2) |
M3 |
693 |
|
| 6 |
Formwork |
M2 |
27,604 |
|
| 7 |
Re – Bar (ASTM A615) |
Ton |
1,292 |
|
| 8 |
Water Stop |
M |
598 |
|
| 9 |
Cutting |
M3 |
88,536 |
|
| 10 |
Filling (Cutting Soil) |
M3 |
88,536 |
|
SOUTH PARS GAS FIELD DEVELOPMENT
DYNAMIC COMPACTION ON RECLAIMED LAND
| Client: |
Petrochemical National Company |
| Contractor: |
FKJ |
| Site Location: |
Boushehr – Asalooyeh |
| Contract Price: |
6,400,000,000.00 Rls |
| Contract Duration: |
7 months |
| Personnel Employed: |
30 persons |
Bill of Quantities
| No. |
Contract Item |
Unit |
Contract
Quantity |
Executed Quantity |
| 1 |
Compaction – 1st Layer |
M2 |
60,000 |
|
| 2 |
Backfill |
M3 |
180,000 |
|
| 3 |
Compaction – 2 nd Layer |
M2 |
60,000 |
|
SOUTH PARS GAS FIELD DEVELOPMENT
PERPENDICULAR TO COAST JETTY
| Client: |
Petrochemical National Company |
| Contractor: |
FKJ |
| Site Location: |
Boushehr – Asalooyeh |
| Contract Price: |
1,900,000,000.00 Rls |
| Contract Duration: |
1.5 months |
| Personnel Employed: |
150 persons |
Bill of Quantities
| No. |
Contract Item |
Unit |
Contract
Quantity |
Executed Quantity |
| 1 |
Extract, Load, Transport, Dispose, Grade & Compact M2 60,000 |
| |
0 – 100 kg |
M3 |
35,000 |
35,000 |
| |
100 – 500 kg |
M3 |
13,000 |
13,000 |
| |
0.5 – 3 Tons |
M3 |
5,000 |
5,000 |
| |
Greater than 3 Tons |
M3 |
2,000 |
2,000 |
SOUTH PARS GAS FIELD DEVELOPMENT
BANK CONSTRUCTION & LAND GRADING
| Client: |
Petrochemical National Company |
| Contractor: |
FKJ |
| Site Location: |
Boushehr – Asalooyeh |
| Contract Price: |
2,000,000,000.00 Rls |
| Contract Duration: |
1.5 months |
| Personnel Employed: |
60 persons |
Bill of Quantities
| No. |
Contract Item |
Unit |
Contract
Quantity |
Executed Quantity |
| 1 |
Extract, Load, Transport, Dispose, PUSH, Grade |
| |
Soil & Rock Material |
M3 |
400,000 |
400,000 |
SOUTH PARS GAS FIELD DEVELOPMENT
PHASES 6, 7 & 8
Camp3
| Top soil: |
23,489 m3 |
| Cut: |
651,051 m3 |
| Filling: |
600,000 m3 |
| Fencing: |
4000 m3 |
| Engineering: |
%6 contract price |
SOUTH PARS GAS FIELD DEVELOPMENT PHASES 6, 7 & 8
CIVIL WORK IN FLARE AREA
| Client: |
Joint venture of TEC / IDRO / JGC/DIC |
| Contractor: |
FKJ |
| Site Location: |
Boushehr – Asalooyeh |
| Contract Price: |
20,000,000,000 RLS |
| Contract Duration: |
8.5 months |
| Personnel Employed: |
250 persons |
Bill of Quantities
| Rebar: |
348 tons |
| Embedded steel plate: |
54 tons |
| Form work: |
11,234 m2 |
| Concrete: |
5,000 m3 |
| Stone pitching: |
50,000 m2 |
| Gabion : |
9,000 m3 |
SOUTH PARS GAS FIELD DEVELOPMENT
EARTH WORK IN FLARE AREA
| Client: |
Joint venture of TEC / IDRO / JGC/DIC |
| Contractor: |
FKJ |
| Site Location: |
Boushehr – Asalooyeh |
| Contract Price: |
25,000,000,000 RLS |
| Contract Duration: |
6 months |
| Personnel Employed: |
90 persons |
Bill of Quantities
| Cutting: |
214,017 m3 |
| Cutting by hammer: |
29,897 m3 |
| Fill: |
33,785 m3 |
| Disposal: |
208,767 m3 |
SOUTH PARS GAS FIELD DEVELOPMENT
PHASE 9, 10 SITE PREPARATION WORKS FOR FLARE ROUTE
| Client: |
Oil industries engineering and construction (OIEC) |
| Contractor: |
FKJ |
| Site Location: |
Boushehr – Asalooyeh |
| Contract Price: |
7,400,000,000 Rls |
| Contract Duration: |
5 months |
| Personnel Employed: |
80 persons |
Bill of Quantities
| Cutting: |
130,000 m3 |
| Cutting by hammer: |
10,000m3 |
| Blasting: |
60,000m3 |
| Disposal: |
100,000m3 |
| Filling: |
50,000 m3 |
|